UWE cut energy costs by £63,593 and offset carbon emmissions by 56,938kg yearly
UWE redeveloped their enterprise park and requested an upgrade to their existing solar setup. We installed 586 x 475W panels across two roofs spanning three elevations, using a Bauder mounting system to preserve the roof warranty.
To boost solar capacity by 260kW, we fitted three 60kW and one 80kW Solis inverters. Fire switches were integrated into the building’s fire control system to meet insurance requirements, and all inverters were connected to the internet for remote monitoring.
£1.6M lifetime ROI
Over the system's 25 year lifetime, it will yield over £1.6m in savings for the University of the West of England.
Energy Generation
Over the course of a single year, this system will generate 264,971kWh of green energy.
Explore solar for business with Comera Energy
Find out how Comera Energy can cut your business energy costs with high-performance solar designed for fast return and minimal upkeep.

Business projects
Solar PV installation for a cental london 50 storey tower.
A 50-storey landmark tower in central London, now the UK’s tallest commercial building to achieve BREEAM Outstanding, features a photovoltaic array installed by Comera Energy on the 48th floor, with a bespoke frame to withstand high wind loads and integration with fire safety systems.
Yearly Energy
20,533kWh
Lifetime Saving
£130,923
Yearly Saving
£5,236
C02 offset
4,253kg p/y
Solar PV installation for a leisure centre in Burgess Hill.
The Triangle Leisure Centre in Burgess Hill offers a gym, pool, soft play, party spaces, and sports facilities. Comera Energy designed, supplied and installed a photovoltaic system on its Kingspan trapezoidal roof using a Renusol mounting system, fully integrated with the building’s fire safety systems.
Yearly Energy
216,229kWh
Lifetime Saving
£1,378,460
Yearly Saving
£55,138
C02 offset
44,774kg p/y
Solar PV installation to W & T Blocks at Frenchay Campus, UWE Bristol.
As part of its 2030 development strategy, the University of the West of England is prioritising sustainability, with solar energy playing a key role. Comera Energy designed, supplied and installed a photovoltaic system on the W & T Blocks at Frenchay Campus, integrating it with the building’s fire safety systems.
Yearly Energy
264,971kWh
Lifetime Saving
£1,689,215
Yearly Saving
£67,568
C02 offset
56,938kg p/y
Solar PV installation to Blavatnik School of Government
Comera Energy were engaged to design, supply and install the photovoltaic installation to the new building which would host one of Oxford’s newest departments, the Blavatnik School of Government. The building was designed by Herzog & De Meuron Architects formed in an irregular stack of circular blocks in glass and concrete.
Yearly Energy
29,881kWh
Lifetime Saving
£190,491
Yearly Saving
£7,619
C02 offset
13,700kg p/y
Solar PV installation to Science Creates, Bristol
Comera Energy were engaged to design, supply and install the photovoltaic installation for Science Creates in Bristol. Science Creates is a Bristol based incubator project for high tech businessess.
Yearly Energy
91,667kWh
Lifetime Saving
£584,352
Yearly Saving
£23,374
C02 offset
21,359kg p/y
Solar PV installation to Bromsgrove School Cafeteria catering for 1,400 students per day.
This project is the refurbishment and extension of the existing dining hall at the prestigious Bromsgrove School, providing a state of the art food hall that can cater for 1,400 students a day. The proposals aimed to address the inefficiencies of the building which included the provision of a roof mounted solar array.
Yearly Energy
31,407kWh
Lifetime Saving
£200,194
Yearly Saving
£8,007
C02 offset
7,323kg p/y